3.3 CAST IN PLACE INSTALLATION PROCEDURES

A.

Temperature affects the setting time and rate of strength of

concrete, standard ACI procedures for storing, mixing, and placing

concrete in hot or cold weather are recommended. See ACI 305

“Standards on Hot Weather Concreting," or ACI 306 “Standard on

Cold Weather Concreting.”

B.

Provide expansion and control joint width indicated in drawings.

All joint materials used follow manufacturer’s directions and

instructions.

1.

Expansion joints must be carried through all layers of installation

materials including warning panels, concrete substrate and steel

reinforcing. Joints should be spaced typically 8’ to 12’ in both

directions. All perimeter edges of ramps or blended transitions

should have expansion joints. (Refer to ACI 360R guidelines for

details on placement, size and specifications of material)

C.

Position forms for proper grade, slopes anduniformslab thickness.

Consult contract documents for details on reinforcement and joint

placement to prevent random cracking.

D.

The concrete specified shall conform to contract documents

with a maximum slump of 4”. Concrete shall be poured and

finished to the proper grade and slope prior to warning panel

placement. Concrete thickness shall be increased 1” in depth

beneath area receiving warning panels.

E.

Consult contract documents for more information on locations

to receive detectable warning panels.

1.

Monolithic poured curb and sidewalk - place panels 6” to 8”

from curb line.

2.

Existing curbs - place panels 8” from curb line to allow 2” of new

concrete in front of panels.

3.

Install across the full width of ramp or blended transition a

minimum 24” in depth.

F.

Recess panels below finish grade with

INSTALaTACT®

installation

template tool before initial concrete set and level base with wood

float to leave an open surface.

G.

Pre-dampen back of

CASTinTACT®

panels with potable water.

Apply 1/8” thickness of

CASTinTACT® Wet Set PreMix

(3:1 ratio of

powder to potable water) or (1:1:

½

ratio of Portland cement, clean

masons sand and potable water). Work into textured surface

on back of panel with rubber float for 100% surface coverage.

Alternatively a scrub coat of fresh concrete removed from the

INSTALaTACT®

tool can be used as a parge coat.

H.

Install Tactile Panels immediately in fresh concrete and lightly

tap panels to grade using a rubber mallet to insure bond and 100%

surface contact.

Wedge or flared edge of panel facing the

curb and square edges of panel joints butted together

. Base of

truncated dome should be flush with adjacent surfaces to permit

proper drainage and eliminate tripping hazard between surfaces.

Tolerance between tactile panels and surrounding surfaces is

1/16” maximum. Immediately after placement re-check slope

and elevation for proper grade.

ALTERNATE (EXTREME CLIMATES) Leave a 3/16” gap between

square cut panels joints and seal with a compatible elastomeric

sealant conforming to ASTM C920. Follow sealant manufacturer’s

recommendations for jointpreparationand installationprocedures.

Protect from traffic until sealant cured.

I.

Finish surrounding concrete flush with tactile panels. Edge

around panels with 1/8” radius edger, install control joints and

finish in accordance with project specifications.

J.

Finish joints per specifications. Follow all manufacturer’s

recommendations for joint preparation and installation

procedures.

K.

Clean fresh dried concrete residue off panels with a stainless

steel wire brush and rinse with clean water and hydra sponge to

ensure a clean appearance.

L.

Fresh concrete surrounding tactile panels should be cured in

accordance with ACI 308. Use a curing compound meeting ASTM

C 309. PROTECT PANELS WITH

PROTECTaTACT

OR SIMILAR WHILE

SPRAYING CURING COMPOUND.

3.4 CLEANING

A.

Remove all unused material, tools, and equipment. Dispose

of properly.

B.

If the detectable / tactile surface requires, clean the panels in

accordance with

CASTinTACT® Cleaning and Maintenance Guide

.

3.5 PROTECTION

Protect the

CASTinTACT®

Warning Panel surface from traffic until

desired strength is achieved. If necessary, protect panels with

plywood and a underlayment layer of non-staining, non-woven

curing blanket until acceptance of work. Secure plywood if needed.

3.6 STORAGE

Store products under cover in manufacturer’s unopened

packaging until ready for installation. Store pallets on supported

flat surface. DO NOT DOUBLE STACK PALLETS.

Early Entry - Fresh Set

Concrete Tactile Warning Panels

CASTinTACT

®